Since commissioning in April 2014 the turbine has performed well and has had almost no down time. Annual production figuresĀ from October 2015 – December 2015 were a total of 621 MWh. 2016 figures are shown in the table below.

Cumulatively, the turbine has generated 1,533 MWh exceeding the P90 cumulative estimate of 1,410 MWh in the last reporting period. The unit is performing better than expected!

Output of BCT Wind Turbine 2016 & 2017

2017Output (MWh) - Approx2016Output (MWh) - Approx
January218January221
February204February197
March167March167
April 191April147
May134May148
June180June115
July151July144
AugustAugust152
SeptemberSeptember150
OctoberOctober146
NovemberNovember192
DecemberDecember212